

At the suggestion of several collaboration members, I would like
to start sending NUSEL-Homestake updates out every several
weeks. The collaboration has (in record time) gone through a series
of reviews: the NSAC and HEPAP Long-Range Plan exercises,
two site reviews by the Physics Division of the NSF, two
NRC reviews (Quarks and the Cosmos and Neutrino Facilities reviews).
This consumed a lot of collaboration time, but to our credit,
it has kept the creation of a deep underground US laboratory
very much on the front burner scientifically and in
Washington.
The NRC NFAC Barish Report has been submitted to Marburger. The
NSF internal process is not very transparent, but the normal
course of events would entail Science Board review of
NUSEL next.
VERSION #2 PROPOSAL
The NUSEL-Homestake Executive Committee decided this week to
draft a version #2 proposal, to replace the one submitted in
early June, 2001. There are a number of reasons for this:
1) The community has done a great deal of work at the
Lead physics and earth science meetings, at NESS02, and in
recent preparations for detector presentations to NSAC and
HEPAP. Many of you helped draft the white papers that are
archived on the NUSEL web page. We have a much better
feel for readiness and scope of future NUSEL projects.
Thus we intend to incorporate much of this material
into a Science Book, with the resulting project timeline
helping guide development of NUSEL.
2) There have been crucial advances in our understanding of
the Homestake site. The original proposal called for
a costly extension of the Yates shaft (from 4850 to 7400 ft).
Our engineers have proposed an alternate and clearly
superior design which avoids this. Scientific access
to the 4850, 7400, and 8000 ft levels will be provided by the Ross
and #6 shafts, while long-term mining capability is
retained, employing the Yates and #4 shafts. A systematic
series of shaft and lift improvements will be
undertaken so that the Ross/#4 provides nearly
clean-room-quality transport of massive loads from the
surface laboratory to depth, while the Yates and #4 can be placed
into service or taken out of service, as needed. Dual access
will be maintained to all levels.
A split-level lab -- physics at both the 4850 and
7400 ft levels -- will give experimentalists some
flexibility in siting their detectors while helping distribute
the ventilation load. A proton decay/long baseline
detector could be installed at 4850 ft to minimize
hoisting costs, while experiments requiring
greater depth -- examples include most double beta
decay, pp solar neutrino, and next-to-next-generation
dark matter detectors -- would be placed
at the deep level.
The new design incorporates 5-ft ventilation shafts
that will connect scientific levels to other nearby
major drifts. This will allow our ventilation engineer
to keep scientific areas clean, even while further
hall excavations are ongoing. One goal of NUSEL-Homestake
is to maintain the ability to provide state-of-the-art
designer cavities for experiments, as future needs arise.
3) The new proposal will reflect Lead/NESS02 suggestions for a
more sophisticated low-level counting facility and instrumentation
for our earth science and geomicrobiology members.
A NUSEL earth science steering committee has been
formed to help us with aspects of the new proposal.
Homestake is of special interest to the earth science
community because the mine offers an extensive network of
drifts important in meeting the instrumentation
goals of the "EarthLab" proponents, while the
geomicrobiologists have discovered thermophilic
methanogens at the 8000 ft level. Homestake rock
is ancient, with isolated pockets of water,
important for the geomicrobiologists hoping to
discover unique microbial colonies. The
geomicrobiologists require clean room facilities
and a drilling rig capable of reaching below
16,000 feet -- facilities we will include in the
version #2 proposal.
We envision the version #2 proposal being authored by
the full collaboration, since so much of the
ground work has been done by this community.
We hope to complete the Science Book by early
April and the full version #2 proposal by the summer.
MINE STATUS
Barrick continues to maintain the mine while completing
its reclamation tasks. There is no near-term
threat of flooding. Barrick is concerned (as we are)
about an extended NSF decision process -- they have
expressed unwillingness to accept federal support
for maintaining Homestake when NUSEL is not an
approved NSF project. Nevertheless recent statements from
Homestake Mine managers appear positive to us.
The state governorship changed in January. The
new governor, Mike Rounds, has asked his brother and
key advisor, Jamie Rounds, to handle NUSEL. Jamie
and Mike have met with the NUSEL PI, and have talked
to several others in the collaboration. The
new administration has many other pressing issues
on its plate, and NUSEL is a complex
project. Thus our view has been to remain patient
while the state decides how it can take on
ownership of the needed portions of the
Homestake site.
Best regards,
for the NUSEL Executive Committee
A. Baha Balantekin, Wisconsin
Wick Haxton
Tom Bowles, LANL
Janet Conrad, Columbia
Sherry Farwell, South Dakota School of Mines & Technology
Ken Lande, Pennsylvania
Kevin Lesko, LBNL
Bill Marciano, BNL
Marvin Marshak, Minnesota
Tullis Onstott, Princeton
Mike Shaevitz, Columbia
John Wilkerson, Washington